    A project schedule completion date will change if ().
    A: the critical path is reduced
    B: the contingency is no longer available
    C: no float time is available
    D: project resources are reduced
  • A

    内容

    • 0

      You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______. A: all stakeholders in the performing organization B: all project stakeholders C: project team members and the project sponsor D: people noted in the communications management plan

    • 1

      One of the types of cost estimation is Order of Magnitude. This estimate ______. A: is performed when detailed information is available B: is performed when little if any information is available C: is used in the beginning of the project conceptualization D: B and C

    • 2

      (9) are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion, they may also exert influence over the project and its results. A: Controls B: Baselines C: Project stakeholders D: Project managers

    • 3

      The(  )provides the project manager with the authority to apply organizational resources to project activities。

    • 4

      Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives