What does a negative Schedule Variance indicate
A: The project is behind in the schedule.
B: Up-scope is causing cost overruns.
C: The project is ahead of schedule.
D: The project is on schedule.
A: The project is behind in the schedule.
B: Up-scope is causing cost overruns.
C: The project is ahead of schedule.
D: The project is on schedule.