    During project execution, a new ISO version of standard 9000 is issued. The project team meets with the quality department to determine how the standard will apply to the project. Which part of the quality process is this
    A: Quality analysi
    B: Quality assuranc
    C: Quality contro
    D: Quality plannin
  • D

    内容

    • 0

      ● Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results. (74) A. quality planning B. quality assurance C. quality performance D. quality control

    • 1

      The new company has launched a __________ project to improve the quality of service.

    • 2

      ● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs

    • 3

      A team member notices the project manager that a quality measurement for the project can not be met. What should the project manager do A: Notify managemen B: Hold a team meetin C: Look for alternative ways to meet the quality leve D: Ask management tp come up with option