Variance analysis include ( )
A: Schedule variance
B: Cost variance
C: The schedule performance index
D: The cost performance index
A: Schedule variance
B: Cost variance
C: The schedule performance index
D: The cost performance index
举一反三
- The evaluation index of variance analysis in EVM include ( )。 A: Schedule variance (SV) B: Cost performance index (CPI) C: Cost variance (CV) D: Project performance index (PPI)
- One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and (). A: divide it by the schedule performance index B: multiply it by the schedule performance index C: multiply it by the cost performance index D: divide it by the cost performance index
- Standard cost variance analysis表示标准成本分析
- Standard cost variance analysis表示标准成本分析 A: 正确 B: 错误
- What does a negative Schedule Variance indicate A: The project is behind in the schedule. B: Up-scope is causing cost overruns. C: The project is ahead of schedule. D: The project is on schedule.